BP

Nov        2002    North Sea          Removal of LEO actuator cap               Completed

Feb       2003    S. North Sea     Wellhead sealant Hanger neck              Still maintaining seal

                                                metal to metal on unmanned

                                                platform

July      2003     Gt Yarmouth      Housing break out tool                          Design and manufacture

Mar       2004     UK

                    Sealant 7” wellhead                             Still maintaining seal

Apr       2004     Gt Yarmouth      Control line cleaning gels                      Completed

May      2005     Trinidad            Sealant:/isolation40” ball valves              Refurbished

Dec      2005     North Sea          Wellhead sealant 9-5/8”                        Still maintaining seal

June     2006     Gt Yarmouth      Design and manufacture of clamps        Bespoke engineering project

                                                and protectors

Dec      2005     North Sea          Control line cleaning gels                      Completed

Dec      2005     North Sea          Large void sealant / filler                       Completed

Dec      2005     Gt Yarmouth      Corrosion protection coating                  Completed

Aug      2006     North Sea          Corrosion protection coatings                Completed

Mar      2007     North Sea          Large void sealant  + isolation barrier      Still maintaining seal