Aug 2002 North Sea Design and manufacture actuator Completed
caps modification view plates
Oct 2002 North Sea Design and manufacture actuator Completed
caps modification view plates
Nov 2002 North Sea Design and manufacture actuator Completed
caps modification view plates
Dec 2002 North Sea Design and manufacture actuator Completed
caps modification view plates
Jan 2003 North Sea Design and manufacture actuator Completed
caps modification view plates
Feb 2003 North Sea Design and manufacture actuator Completed
caps modification view plates
Aug 2005 St Fergus Sealant: flange repair Completed
Sept 2005 North Sea Large void sealant / filler Completed
Oct 2006 North Sea Design engineering 20” isolation Completed
pipe clamp
Apr 2007 North Sea Corrosion protection: electrical boxes Completed